OIL & GAS SECTOR INSIGHT 31/01/2022
Refineries Rehabilitation Gulped N100bn In 2021, Says NNPC
The Nigerian National Petroleum Company Limited has said it spent N100bn on refineries’ rehabilitation in 2021 and that funds were pumped into revamping the facilities on a monthly basis last year.
It disclosed this in a report on the funding performance of the oil firm from January to December 2021, which was seen in Abuja on Sunday.
Although no refinery was mentioned in the report, Nigeria’s refineries had been under the management of NNPC, as the rehabilitation of one of the facilities, Port Harcourt Refining Company, had been ongoing.
The other refineries under the NNPC’s management include the Kaduna Refining and Petrochemical Company, as well as the Warri Refining and Petrochemical Company.
In the NNPC’s latest funding performance report, the firm stated that N8.33bn was spent monthly for a period of 12 months beginning from January to December 2021 on refinery rehabilitation.
The Federal Government has been making moves to get the country’s refineries back on stream, as Nigeria currently imports bulk of its refined petroleum products.
This has resulted in humongous subsidy spendings by the NNPC, the sole importer of petrol into Nigeria for more than four years and counting.
The report stated that the government had made an initial payment of $194m, being the 15 per cent advance payment required for the rehabilitation of the facility, to Tecnimont SpA of Italy.
This was contained in the financial status update of the rehabilitation of PHRC as the project was financed by an equity contribution by its sponsor and loan by lenders (AfreximBank).
The report indicated that the Engineering, Procurement, Construction, Installation, and Commissioning contract price remained at $1.397bn lump sum with $162m as provisional sum, bringing the total project cost to $1.559bn, as approved by the Federal Executive Council.
The Federal Executive Council approved the contract for the EPCIC of the Port Harcourt refinery on March 17, 2021, and work on the facility commenced last year.
The council approved the award of the PHRC EPCIC contract to Tecnimont in March, and the contract agreement was signed on April 6, 2021, as the report seen in Abuja on Friday indicated that additional funds had been processed to ensure the continued rehabilitation of the plant.
In August last year, the Federal Executive Council approved the sum of $1.48bn for the rehabilitation of both Warri and Kaduna refineries.
The Minister of State for Petroleum Resources, Chief Timipre Sylva, announced this at the end of one of the weekly FEC meetings held in Abuja.
Sylva had explained that the rehabilitation of Warri and Kaduna refineries would be awarded to Messers Saipem SPA and Saipem Contracting Limited at the combined total sum of $1.484bn and would be rehabilitated in three phases of 21, 23 and 33 months.